Question
The details of the activities of a construction project are given below.
| Activity Identification | Immediate Predecessor | Duration (days) |
| A | - | 14 |
| B | A | 15 |
| C | B | 25 |
| D | A | 20 |
| E | D | 12 |
| F | A | 9 |
| G | F | 21 |
| H | G | 24 |
| I | C | 16 |
| J | B, I | 18 |
| K | H | 20 |
| L | K | 6 |
| M | E | 8 |
| N | J, C | 7 |
| P | M, G | 10 |
Construct a project network diagram for this problem, determine the critical path and state the expected project completion time and total float.
Answer :
Word Count : 401
The project network follows the given precedence relationships (A is the start). Forward and backward passes give the early/late times and total float shown below. Activity | Pred. | Duration | ES | EF | LS | LF | Total Float (TF) A | – | 14 | 0 | 14 | 0 | 14 | 0 B | A | 15 | 14 | 29 | 14 | 29 | 0 C | B | 25 | 29 | 54 | 29 | 54 | 0 D | A | 20 | 14 | 34 | 45 | 65 _______ ______ ___ ____ _____ ____ ____ ________.
_________ ____ _______ _________ _______ ___ __________ ___ ______ ___.
_________ _________ __________ __________ ____ __________ _______ _____ __________ _______.
_______ ___ ____ _______ __________ _________ __________ ________ ____.
_________ _________ ___ ______ _______.
____ _______ ________ ___ ________ ________ _______ _______ ________.
________ _____ _________ __________ ___ _________ ___ ___.
________ _________ __________ ___ _______ _____ _____ _________ _____ _______.
__________ ____ _______ _____ _________ ______ ____ __________ ____ ___ ________ ___.
___ _______ ________ _______ _____ ___ _____ ________ ____ ___ ________ _____.
_______ _____ __________ ________ _________ ________ _________ ____ __________ _________.
____ _______ _________ ______ ______ ______ __________ __________.
___ __________ __________ _______ ________ ___ __________ _______ ___ _________.
______ _______ ____ ____ ______ _____ _________ ________ _____ _________.
_________ ________ _______ ____ ___.
________ ______ _______ ______ ____.
____ _________ ______ ____ ________.
_____ ___ ________ ________ __________ ________ ____ __________.
__________ _________ __________ ____ ______ ________ ________ ____ _____.
_____ ________ _____ ____ ________.
________ ________ ________ _______ ___.
_________ ________ ______ ___ ___ ______ ______ ___ ________ ___ ________.
___ _______ _________ ___ ______ _______ ____ ________ ____ __________ ________ ______.
__________ _________ ___ __________ ______ _______ ___ _______ _________ ______.
_______ _____ _________ ____ _________ _____ _______ ___ _______ ________.
_________ _____ _____ ________ _______.
__________ _____ _________ ________ _____ ________ ________ ____ ___ _____ ____.
________ ___ ___ _______ _______ ___ ________ _____ _________ ____.
______ ________ __________ ________ ________ ________ _________ __________ ___ ________ _____ _______.
_________ _____ _________ _______ ___ _______ ________.
__________ _______ ______ ____ ____.
_____ ______ ___ _____ _____ __________ ____ ___ _____ ______ ___ ______.
_________ ____ ____ __________ _______ _____ _____.
_________ ______ ___ _____ _______ _______ _____ __________ _________.
___ ___ _____ ____ ___ __________ ______.
Get Full Answer on WhatsApp
The project network follows the given precedence relationships (A is the start). Forward and backward passes give the early/late times and total float shown below. Activity | Pred. | Duration | ES | EF | LS | LF | Total Float (TF) A | – | 14 | 0 | 14 | 0 | 14 | 0 B | A | 15 | 14 | 29 | 14 | 29 | 0 C | B | 25 | 29 | 54 | 29 | 54 | 0 D | A | 20 | 14 | 34 | 45 | 65 _______ ______ ___ ____ _____ ____ ____ ________.
_________ ____ _______ _________ _______ ___ __________ ___ ______ ___.
_________ _________ __________ __________ ____ __________ _______ _____ __________ _______.
_______ ___ ____ _______ __________ _________ __________ ________ ____.
_________ _________ ___ ______ _______.
____ _______ ________ ___ ________ ________ _______ _______ ________.
________ _____ _________ __________ ___ _________ ___ ___.
________ _________ __________ ___ _______ _____ _____ _________ _____ _______.
__________ ____ _______ _____ _________ ______ ____ __________ ____ ___ ________ ___.
___ _______ ________ _______ _____ ___ _____ ________ ____ ___ ________ _____.
_______ _____ __________ ________ _________ ________ _________ ____ __________ _________.
____ _______ _________ ______ ______ ______ __________ __________.
___ __________ __________ _______ ________ ___ __________ _______ ___ _________.
______ _______ ____ ____ ______ _____ _________ ________ _____ _________.
_________ ________ _______ ____ ___.
________ ______ _______ ______ ____.
____ _________ ______ ____ ________.
_____ ___ ________ ________ __________ ________ ____ __________.
__________ _________ __________ ____ ______ ________ ________ ____ _____.
_____ ________ _____ ____ ________.
________ ________ ________ _______ ___.
_________ ________ ______ ___ ___ ______ ______ ___ ________ ___ ________.
___ _______ _________ ___ ______ _______ ____ ________ ____ __________ ________ ______.
__________ _________ ___ __________ ______ _______ ___ _______ _________ ______.
_______ _____ _________ ____ _________ _____ _______ ___ _______ ________.
_________ _____ _____ ________ _______.
__________ _____ _________ ________ _____ ________ ________ ____ ___ _____ ____.
________ ___ ___ _______ _______ ___ ________ _____ _________ ____.
______ ________ __________ ________ ________ ________ _________ __________ ___ ________ _____ _______.
_________ _____ _________ _______ ___ _______ ________.
__________ _______ ______ ____ ____.
_____ ______ ___ _____ _____ __________ ____ ___ _____ ______ ___ ______.
_________ ____ ____ __________ _______ _____ _____.
_________ ______ ___ _____ _______ _______ _____ __________ _________.
___ ___ _____ ____ ___ __________ ______.
Get Full Answer on WhatsApp
IGNOU NEWS
Assignment Submission Last Date Extended Till 30 June 2026 Click Here★★★IGNOU June 2026 TEE Date Sheet Released Click Here★★★