Question

Draw a project network for the following jobbing production.

 

Activity     Description    Preceded by Time (Weeks)
A Market research   15
B Make drawings   15
C Decide production policy A 3
D Prepare sales programme A 5
E Prepare operation sheets B, A 8
F Buy materials B, C 12
G Plan labor force E 1
H Make tools E 14
I schedule production D,G 3
J Produce product F,H,I 14

a. Construct the project network diagram.

b. Calculate the time estimates (EST, EFT, LST and LFT) in the above project.

c. Find the critical path and critical activities and project duration in the above project?

01 Apr 2022
Answer :
Word Count : 402

a. Project Network Diagram:

The project network diagram can be constructed based on the given activities and their dependencies.

____ _______ ______ ____ ___ _______ ___ ___ __________ ___.
____ _________ ______ ____ _______ ____.
_________ ____ _____ ______ _________ ________ _____ ____ __________ _______ ____.
__________ ___ __________ ____ ___ ____ ______ ____ _________ ________ __________ ________.
____ __________ ____ _________ ___ ________ _______ _____ __________ ______.
________ ________ ______ _________ _____ ______ _________.
______ _________ _____ ____ _________.
__________ ____ ________ _____ ____ ________ ___ ____ _____.
_______ ________ _________ _____ ___ _________ ____.
_______ ___ ____ ____ ____ ____ _____.
____ ______ ____ __________ _________ ____ _____ ________.
___ ________ _______ _____ _________ _____ ___ _____ ________ __________ ________ ________.
__________ _____ ____ _______ _________ _______ _______ _________.
___ ____ _____ ___ ___ ___ ____ __________ _________ _________.
____ ___ ______ ____ _______ __________ ____ _________ ___ ________.
__________ _____ ________ ______ _____ _________ ____ _________ __________.
______ _____ ________ ___ ______ ____ ___ __________ ______.
____ _______ ________ ____ ______ ________ _______ _______ _________.
_________ ________ _______ ________ ________ ______ ____.
___ ________ __________ ___ _________ ___ ________ ________ ______ _____.
____ ______ _________ __________ _________ ___ _____ ___ __________ ________ ______.
_____ ___ _________ _______ ___.
______ ___ ____ ______ _____.
_________ ______ ______ ______ ___ __________ ______ _____ ___ ______.
______ ______ _______ _______ ______ __________ ___ ________ ___ __________ _______ _______.
_________ _____ ___ _____ ________ __________ ___ ___ ___ __________ _________ _____.
__________ ____ _________ __________ _____ _________ ________ ___ ____ ___ _________.
_____ ______ _________ ____ _______ ________ ___ ___.
____ _________ ________ _____ ___ _________ ______ ________.
_____ _________ _________ ________ _______ _________ ________ ________.
_________ ______ __________ ____ ______.
_____ ____ _________ _______ ________ ______ ____ _______ ______ ____ ________ _____.
___ _______ _______ ___ ______ _____ _________ ______ ___ ___ _________ ______.
______ _______ __________ ________ __________ __________ ________.
Get Full Answer on WhatsApp
Activity Description Preceded by Time (Weeks)
A Market research None 15
B Make drawings None 15
C Decide production policy A 3
D Prepare sales programme A 5
E Prepare operation sheets B, A 8
F Buy materials B, C 12
G Plan labor force E 1
H Make tools E 14
I Schedule production D, G 3
Activity     Description    Preceded by Time (Weeks)
A Market research   15
B Make drawings   15
C Decide production policy A 3
D Prepare sales programme A 5
E Prepare operation sheets B, A 8
F Buy materials B, C 12
G Plan labor force E 1
H Make tools E 14
I schedule production D,G 3
J Produce product F,H,I 14

What do you mean by an integrated project information system? Draw an MIS for 4- storeyed brick and residential building assuming that there is a magnificent component of marbling, tiling and sanitary work.

Project environment

What is project quality management? Describe the quality control procedure in project management existing in an organization that you know.

IGNOU NEWS
Assignment Submission Last Date Extended Till 30 June 2026 Click Here★★★IGNOU June 2026 TEE Date Sheet Released Click Here★★★
Top