Draw a network diagram for the activities given below and determine the critical path.
| Activity | Description | Predecessor | Duration (Months) | |
| A | Design Plant | - | 12 | |
| B | Select Site | A | 8 | |
| C | Select Vendor | A | 4 | |
| D | Select Personnel | A | 3 | |
| E | Prepare Site | B | 12 | |
| F | Manufacture Generator | C | 18 | |
| G | Prepare Operations Manual | C | 5 | |
| H | Install Generator | E,F | 4 | |
| I | Train Operators | D,G | 9 | |
| J | Obtain License | H,I | 6 | |