Draw a network diagram for the activities given below and determine the critical path.

Activity Description Predecessor Duration (Months)
A Design Plant - 12
B Select Site A 8
C Select Vendor A 4
D Select Personnel A 3
E Prepare Site B 12
F Manufacture Generator C 18
G Prepare Operations Manual C 5
H Install Generator E,F 4
I Train Operators D,G 9
J Obtain License H,I 6