Question
A software project has been estimated to have 300 Function Points (FP). The project is being developed by a
team with average experience, and the complexity of the project is considered high. The company uses a productivity factor of 10 FP per person-month.
(a) Calculate the estimated effort in person-months.
(b) If the project needs to be completed in 6 months, calculate the estimated team size (number of people required).
(c) Briefly explain what a "Function Point" represents in software estimation and why it is often preferred over Lines of Code (LOC) as a metric.
Answer :
Word Count : 342
The given project has an estimated size of 300 Function Points (FP). The productivity factor of the company is 10 FP per person-month, which means that in one month, a single developer can handle 10 Function Points. To calculate the estimated effort, we divide the total Function Points by the productivity factor. Hence, the effort equals 300 _______ ________ _________ _____ _________ ________ ___ _______ ______ _________ _______ __________.
_____ ___ _____ _________ ____.
__________ ____ ___ ____ ____ ________ _________ _______ _____ _______ _________ ____.
_______ ___ __________ _____ ________ _________ ___.
___ ________ _____ ______ ____.
______ __________ _______ _________ ___.
__________ ________ ________ ________ ______ ____ ______ ________ ___.
___ __________ _________ __________ ______ ______ ___ ___ _________ __________ ________ _____.
______ ____ ______ ______ ___ ___ ___.
_____ _____ ______ ____ ________ __________ __________ ____ _________ _________ __________.
___ ___ _____ ___ _______ _________.
___ ____ ________ ___ ___ _____.
_______ _________ ___ __________ _______ _____ _________ _____ ______.
____ _____ _________ ___ ___ ___ _____ ________ _______ ___ _______ _______.
___ _______ __________ _____ _______ _________ ______ ________ ___ ____ ________.
___ ________ _______ __________ ____ ______ ______ ________ ________ __________ __________ _____.
______ ___ ___ ______ ________ _________.
_________ _____ _______ _________ ______ _______.
_____ __________ ____ _____ ______ ______ ____ ___ ____.
_________ ________ __________ ________ ________ __________ _________ ___ ____ _____ _______.
____ _________ _____ ___ ___ ________ ______ _______ ______ ___.
________ ___ ______ ____ ___ _____ ______.
_______ _______ __________ ______ ______ _____ ___ _______ ___.
_________ ________ ____ ______ ______ _________ __________ ____ _______ ________.
________ __________ __________ _____ ______ ______ _____ ___ ____ ______ _________.
____ _________ ____ ____ _____ ____ ____ ____ _______ ______ ____.
_____ _______ ____ _______ ________.
____ _________ _________ _______ ________.
_____ _________ _____ ________ __________ ___ ____ ___.
________ _______ ______ __________ __________ ________ _________.
_____ ____ _________ __________ _______ ________ ______.
__________ ____ ____ _________ _________ ____.
________ ________ _____ ____ ____.
____ __________ ____ ________ ____.
____ ______ _________ ____ _______.
____.
Get Full Answer on WhatsApp
The given project has an estimated size of 300 Function Points (FP). The productivity factor of the company is 10 FP per person-month, which means that in one month, a single developer can handle 10 Function Points. To calculate the estimated effort, we divide the total Function Points by the productivity factor. Hence, the effort equals 300 _______ ________ _________ _____ _________ ________ ___ _______ ______ _________ _______ __________.
_____ ___ _____ _________ ____.
__________ ____ ___ ____ ____ ________ _________ _______ _____ _______ _________ ____.
_______ ___ __________ _____ ________ _________ ___.
___ ________ _____ ______ ____.
______ __________ _______ _________ ___.
__________ ________ ________ ________ ______ ____ ______ ________ ___.
___ __________ _________ __________ ______ ______ ___ ___ _________ __________ ________ _____.
______ ____ ______ ______ ___ ___ ___.
_____ _____ ______ ____ ________ __________ __________ ____ _________ _________ __________.
___ ___ _____ ___ _______ _________.
___ ____ ________ ___ ___ _____.
_______ _________ ___ __________ _______ _____ _________ _____ ______.
____ _____ _________ ___ ___ ___ _____ ________ _______ ___ _______ _______.
___ _______ __________ _____ _______ _________ ______ ________ ___ ____ ________.
___ ________ _______ __________ ____ ______ ______ ________ ________ __________ __________ _____.
______ ___ ___ ______ ________ _________.
_________ _____ _______ _________ ______ _______.
_____ __________ ____ _____ ______ ______ ____ ___ ____.
_________ ________ __________ ________ ________ __________ _________ ___ ____ _____ _______.
____ _________ _____ ___ ___ ________ ______ _______ ______ ___.
________ ___ ______ ____ ___ _____ ______.
_______ _______ __________ ______ ______ _____ ___ _______ ___.
_________ ________ ____ ______ ______ _________ __________ ____ _______ ________.
________ __________ __________ _____ ______ ______ _____ ___ ____ ______ _________.
____ _________ ____ ____ _____ ____ ____ ____ _______ ______ ____.
_____ _______ ____ _______ ________.
____ _________ _________ _______ ________.
_____ _________ _____ ________ __________ ___ ____ ___.
________ _______ ______ __________ __________ ________ _________.
_____ ____ _________ __________ _______ ________ ______.
__________ ____ ____ _________ _________ ____.
________ ________ _____ ____ ____.
____ __________ ____ ________ ____.
____ ______ _________ ____ _______.
____.
Get Full Answer on WhatsApp
IGNOU NEWS
Assignment Submission Last Date Extended Till 30 June 2026 Click Here★★★IGNOU June 2026 TEE Date Sheet Released Click Here★★★