Solve your IGNOU Doubts
Solve your IGNOU Doubts
Question:

Discuss the various organisational behaviour models.

See Answer →
Question:

Examine the various theories of leadership

See Answer →
Question:

Examine the various theories of leadership

See Answer →
Question:

Discuss the types and components of attitudes.  

See Answer →
Question:

The final table in Phase I of a Linear Programming Problem is given below:

C_{B}

     Basic

    Variables

 0          0          0           0             -1 

 x_{1}       x_{2}        s_{1}         s_{2}          x_{a_{1}}

    Sol.
0        x_{2}

1         1           1      0           0   

-1         0        -1       -1          1

     5
-1         x_{a_{1}}      3
    -1         0        -1       -1           0      -3

Here 1a x is the artificial variable. Does this LPP have a feasible solution? Justify your answer.

See Answer →
Question:

 Write down the equation of adaptive expectations hypothesis. Illustrate it with an example. 

See Answer →
Question:

What are the effects of an expansionary fiscal policy on output and prices?

See Answer →
Question:

Explain the concept of rational expectations. 

See Answer →
Question:

Explain why “balance of payments always balances”. 

See Answer →
Question:

Bring out the salient features of the monetary approach to exchange rate determination. 

See Answer →
Question:

Bring out the salient features of the monetary approach to exchange rate determination. 

See Answer →
Question:

Specify the equation of the IS curve for an open economy. What are the factors that cause a shift in the IS curve?

See Answer →
Question:

How do you reconcile the vertical long run Phillips curve with the downward sloping short run Phillps curve? Explain through a diagram. 

See Answer →
Question:

In an open economy with floating exchange rate, analyse the effectiveness of fiscal policy and monetary policy. 

See Answer →
Question:

Derive the AS curve from the WS and PS relations. Discuss the factors that influence the position of the AS curve.  

See Answer →
Question:

An insurance company has decided to modernize and refit one of its branch offices. Some of the existing office equipments will be disposed of but the remaining will be returned to the branch on completion of the renovation work. Tenders are invited from a number of selected contractors. The contractors will be responsible for all the activities in connection with the renovation work excepting the prior removal of the old equipment and its subsequent replacement. The major elements of the project have been identified as follows along with their durations and immediately preceding element:

          Activity               Description

  Duration

( weeks)

Immediate

Predecessor

     A      Design new premises  14   -
     B  Select the contractor and arrange    details with selected contractor   7   A
     C Arrange storage of equipment to be retained   5   B
      D

Arrange disposal of equipment not to be retained

  2    C
      E Procure new equipment   4   C,G
      F Renovations take place  12   C,D
      G Cleaning after the contractor has finished   2    F
      H Bringing back retained equipment from storage   2   G,E

Draw the network diagram showing the inter-relations between the various activities of the project.

Calculate the minimum time that the renovation can take from the design stage.

Find the effect on the overall duration of the project if the estimates or tenders can be obtained in 2 weeks from the contractors by reducing their numbers.

Calculate the ‘independent float’ that is associated with the non-critical activities in the network diagram.

See Answer →
Question:

An insurance company has decided to modernize and refit one of its branch offices. Some of the existing office equipments will be disposed of but the remaining will be returned to the branch on completion of the renovation work. Tenders are invited from a number of selected contractors. The contractors will be responsible for all the activities in connection with the renovation work excepting the prior removal of the old equipment and its subsequent replacement. The major elements of the project have been identified as follows along with their durations and immediately preceding element:

See Answer →
Question:

Find the shortest route from A to G using Bellman’s Optimality Principle.

Image ignouassignments-ignouacademy-com--p-your-53055

See Answer →
Question:

A fertilizer company distributes its products by trucks loaded at its only loading
station. Both, company trucks and contractor’s trucks are used for this purpose. It
was found out that on an average every 5 minutes one truck arrived and the average
loading time was 3 minutes. 40 percent of the trucks belong to the contractors.
Making suitable assumptions, determine:
 i) The probability that a truck has to wait.
 ii) The waiting time of a truck that waits.
 iii) The expected waiting time of contractor’s trucks per day. 

See Answer →
Question:

Solve the following LPP by simplex method:

Max 9x_{1} +7x_{2} +7x_{3}

Subject to   3x1+ x_{2} +2x_{3} leq 12

                    x_{1},5 x_{2}, +3x_{3} leq 30

                     x_{1}, x_{2}, x_{3} geq 0.

See Answer →
IGNOU NEWS
Assignment Submission Last Date Extended Till 30 June 2026 Click Here★★★IGNOU June 2026 TEE Date Sheet Released Click Here★★★
Top
📞
Call Support Instant phone assistance
🟢
WhatsApp Chat Fast live messaging
Email Us Business enquiries & support